PMI Professional in Business Analysis (PMI-PBA) — Question 124

A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.
What is the most effective way to manage this situation?

Answer options

Correct answer: B

Explanation

The correct answer is B because sharing the new requirements and soliciting feedback allows stakeholders to consider the implications without delaying the meeting. Options A and D involve direct discussion during the meeting, which may not allow for thorough analysis of the new requirements, while C focuses on resource allocation rather than stakeholder communication.