The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?
Answer options
- A. Critical design review
- B. Production readiness review
- C. System requirements review
- D. Test readiness review
Correct answer: A
Explanation
The Critical design review is the appropriate type of review to ensure that the design meets the established requirements and to finalize the requirements baseline. The other options, such as Production readiness review and Test readiness review, focus on later stages of the product lifecycle and do not specifically address the approval of requirements.