PMI Agile Certified Practitioner (PMI-ACP) — Question 97
While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments.
What should the agile coach do?
Answer options
- A. Work with the sponsor to develop team expectations
- B. Provide the customer with a list of deliverables and obtain agreement
- C. Encourage the team to more frequently interact with all stakeholders
- D. Work on finishing upfront product design rather than comprehensive documentation
Correct answer: C
Explanation
The correct answer is C, as encouraging frequent interaction with stakeholders helps improve communication and ensures alignment on expectations, which can aid the team's performance. Options A and B do not directly address the team's internal dynamics and responsibilities, while D shifts focus away from agile principles by emphasizing upfront design over adaptability.