PMI Agile Certified Practitioner (PMI-ACP) — Question 87
An agile team delivered a feature in the last iteration. The product owner, who missed the planning and review meetings, was dissatisfied with feature. The team conducted a retrospective and reviewed the user stories related it.
What should the agile team do next?
Answer options
- A. Ensure that the product owner reviews the acceptance criteria for delivered user stories
- B. Augment the quality assurance and continuous integration processes for delivery
- C. Approach the relevant developers and testers regarding quality issues, in upcoming iterations
- D. Ask the product owner to define the entire scope of delivery two to three iterations in advance
Correct answer: A
Explanation
The correct answer is A because ensuring that the product owner reviews the acceptance criteria allows for alignment on expectations and improves future deliveries. Options B and C focus on quality improvements, which are important, but do not directly address the product owner's dissatisfaction. Option D suggests a proactive approach, but defining the entire scope in advance may not align with agile principles of adaptability and iterative feedback.