PMI Agile Certified Practitioner (PMI-ACP) — Question 47
A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to complete in the market place.
What analysis should the team use to understand the issues?
Answer options
- A. Risk management
- B. Variance and trend
- C. Kano model
- D. Fishbone-diagram
Correct answer: D
Explanation
The Fishbone-diagram, also known as an Ishikawa diagram, helps identify root causes of problems, making it suitable for analyzing delays in the development process. The other options, while useful in different contexts, do not specifically target the identification of underlying issues causing delays.