Midway through a sprint, a scrum team member advises the team of a new requirement that may change the initial scope.
What should the team do?
Answer options
- A. Work on requirements that the product owner may have overlooked
- B. Record the scope creep in the change management log
- C. Add the new requirement to the product backlog
- D. Ask the scrum master to secure additional time and resources
Correct answer: C
Explanation
The correct answer is C because new requirements should be added to the product backlog for prioritization and review by the product owner. Option A is incorrect as it does not follow the process of managing scope changes. Option B does not address accommodating the new requirement in the product backlog, and option D is not a standard practice as it may not be feasible or necessary to secure additional resources.