Midway through a sprint, a scrum team member advises the team of a new requirement that may change the initial scope.
What should the team do?

Answer options

Correct answer: C

Explanation

The correct answer is C because new requirements should be added to the product backlog for prioritization and review by the product owner. Option A is incorrect as it does not follow the process of managing scope changes. Option B does not address accommodating the new requirement in the product backlog, and option D is not a standard practice as it may not be feasible or necessary to secure additional resources.