PMI Agile Certified Practitioner (PMI-ACP) — Question 34
During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to efficiently complete its stories.
What should the team do?
Answer options
- A. Cross-train some members in the automation framework to broaden their capacity with that skill
- B. Ask the product owner to add team members to boost this particular skill set
- C. Send a member to automation framework training when funds are available
- D. Avoid using test automation by swarming on the testing tasks and using manual testing
Correct answer: A
Explanation
The correct answer is A, as cross-training team members in the automation framework directly addresses the skill gap and enhances the team's overall capability. B is less effective because relying on the product owner to add members may not be feasible or timely. C delays the necessary training until funding is available, which could hinder progress. D is counterproductive as it avoids leveraging automation, which the team needs to improve efficiency.