PMI Agile Certified Practitioner (PMI-ACP) — Question 334
The product owner of a team starts the iteration review with a quick walkthrough of the iteration goal, the list of planned stories with status, and a demo of all the stories to the business.
What should the product owner have done differently?
Answer options
- A. Demonstrated only the completed stories and seek stakeholder feedback
- B. Presented the budget situation and review the cost variance
- C. Reviewed the test results to gain confidence from the stakeholders
- D. Presented a demo of all the stories including the work in progress stories
Correct answer: A
Explanation
The correct answer is A because focusing on completed stories allows for meaningful feedback from stakeholders on the finished work. The other options are less relevant to the review's purpose, which is to showcase completed work and gather immediate feedback rather than discuss budget, test results, or work in progress.