PMI Agile Certified Practitioner (PMI-ACP) — Question 327
A customer has difficulty explaining how the highest priority feature will work. What should the agile project manager do?
Answer options
- A. Create a time-boxed spike story to reduce the technical risk of the feature.
- B. Commence an iteration 0 for the customer and the team to investigate the feature.
- C. Facilitate the decomposition of the feature epic into more manageable user stories.
- D. Facilitate a just-in-time exploration of the functionality by the customer and the team.
Correct answer: D
Explanation
The correct answer is D because facilitating a just-in-time exploration allows for immediate clarification and understanding of the feature between the customer and the team. Options A and B do not directly address the customer's difficulty in explaining the feature, while option C focuses on decomposition, which is not the immediate need in this scenario.