PMI Agile Certified Practitioner (PMI-ACP) — Question 325

Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date. What should the agile practitioner do?

Answer options

Correct answer: C

Explanation

The correct answer, C, is appropriate because using a risk burndown chart allows the team to visualize and manage risks effectively over time. Option A is ineffective as it suggests addressing issues only after they have occurred, while B does not provide a proactive approach to monitoring risks. Option D, while useful, does not offer the same level of insight into overall risk management as a risk burndown chart.