Over the last two sprints, a number of potential problems have threatened the team's ability to hit the targeted release date. What should the agile practitioner do?
Answer options
- A. Deal with the issues in a retrospective if they ever come up again.
- B. Create a task board to track issues when they appear.
- C. Identify and monitor issues through a risk burndown chart.
- D. Create an issue log as an information radiator and monitor.
Correct answer: C
Explanation
The correct answer, C, is appropriate because using a risk burndown chart allows the team to visualize and manage risks effectively over time. Option A is ineffective as it suggests addressing issues only after they have occurred, while B does not provide a proactive approach to monitoring risks. Option D, while useful, does not offer the same level of insight into overall risk management as a risk burndown chart.