PMI Agile Certified Practitioner (PMI-ACP) — Question 318
As a team completes their 21st sprint, new information reveals that a number of significant system integrations must be made to ensure the project scope is met. How should the project management plan be adjusted?
Answer options
- A. Holistically at the project level
- B. At the end of each sprint
- C. At a sprint level after each demo
- D. Periodically, at both the release and project level
Correct answer: D
Explanation
The correct answer is D because the project management plan should be adjusted periodically to reflect changes at both the release and project levels to accommodate new integrations. Options A and B are too infrequent for significant changes, while C focuses too narrowly on sprint demos and does not encompass the broader project needs.