A company has decided to use an agile delivery method for launching a new product to improve the customer checkout experience. How should the project manager ensure the experienced predictive delivery teams are capable of adopting the agile model?

Answer options

Correct answer: B

Explanation

The correct answer is B because organizing training and development workshops fosters a collective comprehension of agile practices among all stakeholders, which is crucial for successful adoption. Option A focuses only on team roles without involving broader stakeholder engagement, while C prioritizes senior leadership without directly addressing the teams. Option D limits the application of agile to select deliverables, which does not facilitate a full transition to the agile model.