PMI Agile Certified Practitioner (PMI-ACP) — Question 316
A company has decided to use an agile delivery method for launching a new product to improve the customer checkout experience. How should the project manager ensure the experienced predictive delivery teams are capable of adopting the agile model?
Answer options
- A. Assign agile roles within the team and conduct training for each role to provide understanding of the agile methodology.
- B. Organize training and development workshops to help all stakeholders to form a shared understanding of agile practices.
- C. Plan a transformation to agile delivery methods for senior leadership before starting project implementation.
- D. Apply only agile methods and practices for specific deliverables of the work and assign this work to experienced agile team members.
Correct answer: B
Explanation
The correct answer is B because organizing training and development workshops fosters a collective comprehension of agile practices among all stakeholders, which is crucial for successful adoption. Option A focuses only on team roles without involving broader stakeholder engagement, while C prioritizes senior leadership without directly addressing the teams. Option D limits the application of agile to select deliverables, which does not facilitate a full transition to the agile model.