PMI Agile Certified Practitioner (PMI-ACP) — Question 308

Several potential risks have been identified for a new project that started last month. The project manager is worried that the team is not fully aware of these potential threats.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because creating a prioritized space on the board helps the team visualize risks and track the progress of response actions effectively. Option A only mentions discussion without a visual representation, while B focuses too much on reminders without addressing risk management. Option C involves the sponsor but does not directly engage the team in risk management.