PMI Agile Certified Practitioner (PMI-ACP) — Question 308
Several potential risks have been identified for a new project that started last month. The project manager is worried that the team is not fully aware of these potential threats.
What should the project manager do?
Answer options
- A. Mention the risks during the daily standups and ensure all agreed-upon response actions are discussed by the team.
- B. Remind the team daily about the threats and request a response regarding which risks have been identified and resolved.
- C. Arrange weekly meetings and invite the project sponsor to discuss the importance of the project with the team.
- D. Create a space on the board to prioritize the threats, along with an update on the actions that are in progress and what still needs to be done.
Correct answer: D
Explanation
The correct answer is D because creating a prioritized space on the board helps the team visualize risks and track the progress of response actions effectively. Option A only mentions discussion without a visual representation, while B focuses too much on reminders without addressing risk management. Option C involves the sponsor but does not directly engage the team in risk management.