PMI Agile Certified Practitioner (PMI-ACP) — Question 304
If an individual is working on a project team in a phase delivering an increment, according to the definition of done (DoD), who was that defined by?
Answer options
- A. Project sponsor and project team
- B. Scrum master
- C. Product owner
- D. Stakeholders and project team
Correct answer: A
Explanation
The correct answer is A because the definition of done (DoD) is collaboratively defined by the project sponsor and the project team to ensure alignment on what constitutes a completed increment. Options B, C, and D are incorrect as they either represent roles that do not define the DoD or include stakeholders without the project sponsor's involvement.