PMI Agile Certified Practitioner (PMI-ACP) — Question 298

A product owner worked with the customer to define the success criteria for the launch of a new product in the manufacturing industry. The project team responsible for development is seeking guidance on what to develop first.

Which two actions should the product owner take? (Choose two.)

Answer options

Correct answer: C, E

Explanation

The correct actions are C and E because inviting the customer to the sprint planning meeting ensures that the team understands the customer's priorities, while refining the product backlog helps identify what features are essential for the Minimum Viable Product. Options A, B, and D do not directly address prioritizing development based on customer needs and the MVP, making them less effective in this context.