PMI Agile Certified Practitioner (PMI-ACP) — Question 290

An organization wants to execute a corporate website redesign project using Scrum. There is an experienced pool of agile team members from a previous project, as well as a pool of available internal team members with some Scrum background.

What should be considered when selecting the team?

Answer options

Correct answer: B

Explanation

The correct answer is B because a balanced team with both experts and those with diverse experiences is essential for the project's success, allowing for knowledge sharing and adaptability. Option A focuses too much on past conflicts, which may overlook valuable team dynamics. Option C disregards the benefits of remote collaboration, and option D prioritizes individual performance over team synergy and skill diversity.