PMI Agile Certified Practitioner (PMI-ACP) — Question 267

The team is aware that they will need to integrate a new component to their solution in the next few weeks. The team does not have any experience with this component.

What should the team do next?

Answer options

Correct answer: C

Explanation

The correct option is C because adding a spike allows the team to explore the new component without committing to it fully, which is essential given their lack of experience. Options A and D do not address the immediate need for investigation or learning, while option B places the responsibility solely on the product owner without involving the team's collaborative effort.