PMI Agile Certified Practitioner (PMI-ACP) — Question 262

A new Scrum team is struggling with the various ceremonies of Scrum. Among other things, the product owner and stakeholders find the technical architecture and design presentations during sprint reviews less than informative.

What should the team do?

Answer options

Correct answer: A

Explanation

The correct answer is A, as it directs the team to prioritize demonstrating working software and gathering valuable feedback, which is the primary goal of sprint reviews. Options B and D focus on external input or changing the audience, which does not address the root issue of making reviews more meaningful for stakeholders. Option C fails to recognize that the current format is not meeting stakeholder needs and does not shift the focus to the product itself.