PMI Agile Certified Practitioner (PMI-ACP) — Question 257

A team is building a product in three-week iterations. During the last retrospective, it was identified that there was a 20 percent increase from previous iterations in the number of reported defects and change requests.

Since this is causing the product's value to decrease, what should the team do?

Answer options

Correct answer: D

Explanation

The correct answer is D because improving communication and understanding with the client can help clarify requirements and reduce misunderstandings that lead to defects. Options A and C focus on process adjustments but do not directly address the root cause of the defects, while option B suggests fixing defects before new stories but does not prevent future issues.