PMI Agile Certified Practitioner (PMI-ACP) — Question 250
One of the overseas stakeholders on an agile project has not been actively involved in the project's development. What would be the first step to reengage the stakeholder?
Answer options
- A. Increase the frequency of emails and/or try to call the stakeholder.
- B. Remind the stakeholder of their obligation to engage in the project.
- C. Talk to the stakeholder's superior so they can offer coaching and guidance on project involvement.
- D. Set up a meeting with the stakeholder to modify the working agreement and ensure future engagement.
Correct answer: D
Explanation
The correct answer is D because setting up a meeting allows for direct communication and collaboration to address engagement issues. Increasing emails or calling (option A) may not provide a solution, while reminding the stakeholder of obligations (option B) may create resentment. Talking to the superior (option C) could be helpful, but it does not directly involve the stakeholder in resolving the issue.