PMI Agile Certified Practitioner (PMI-ACP) — Question 239
A new stakeholder has recently joined a project. During a meeting with the scrum master, the new stakeholder tries to understand the status of the project and the remaining tasks for completion.
How should the scrum master inform the new stakeholder?
Answer options
- A. Show the stakeholder the latest release breakdown for the project.
- B. Invite the stakeholder to attend the next sprint review meeting.
- C. Show the stakeholder the progress radiators for the project.
- D. Invite the stakeholder to attend the next sprint planning meeting.
Correct answer: C
Explanation
The correct answer is C because progress radiators visually represent the current status of the project and the remaining tasks, providing clear and immediate insight to the stakeholder. Option A focuses on release breakdowns, which may not show current task status. Option B involves a future event that may not provide immediate answers, and option D is about planning rather than current progress.