An executive notices a kanban board in a highly visible location and expresses concerns to the project manager that too many people will see it. What should the project manager do?

Answer options

Correct answer: C

Explanation

Option C is correct because it highlights the benefits of the kanban board in aiding the team’s work completion and promoting transparency. Option A is impractical, as it would defeat the purpose of visibility. Option B, while valid, does not address the transparency aspect, and Option D would eliminate the benefits of using the kanban board altogether.