PMI Agile Certified Practitioner (PMI-ACP) — Question 224

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the scrum master do?

Answer options

Correct answer: D

Explanation

The correct answer is D because it allows the team to assess the impact of rework on their timeline and make necessary adjustments. Options A, B, and C do not address the underlying issue of rework effectively; they either ignore it or force the team to adhere to an unadjusted schedule, which may lead to further complications.