PMI Agile Certified Practitioner (PMI-ACP) — Question 215

The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.

What should the agile practitioner do?

Answer options

Correct answer: D

Explanation

The correct answer is D because the project retrospective is specifically designed for the team to reflect on their performance and discuss any issues, including fatigue. Options A and B may not provide the right context for a deeper discussion, while option C involves stakeholders who may not be directly relevant to the team's internal dynamics.