PMI Agile Certified Practitioner (PMI-ACP) — Question 210

After conducting the second retrospective with project stakeholders, the customer expresses frustration. The customer wants a more predictable roadmap for the delivery of features and functionalities.

How should the project manager respond to the customer?

Answer options

Correct answer: C

Explanation

The correct answer is C because it focuses on collaborating with the customer to prioritize user stories that maximize business value, allowing for a more tailored and effective release plan. Option A incorrectly suggests that a roadmap is impossible in agile, while B puts the onus on the customer, and D does not actively engage the customer in prioritization and value assessment.