PMI Agile Certified Practitioner (PMI-ACP) — Question 185

An executive requests information regarding a sprint status.
What action should the product owner take?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the information radiator provides real-time visibility into the sprint's progress and is designed for stakeholders to access updates easily. Options A, C, and D are less efficient since they either require the executive's presence or do not utilize the tools specifically meant for sprint updates.