PMI Agile Certified Practitioner (PMI-ACP) — Question 185
An executive requests information regarding a sprint status.
What action should the product owner take?
Answer options
- A. Invite the executive to the stand up
- B. Direct the executive to the information radiator
- C. Personally meet with the executive
- D. Email the requested information to the executive
Correct answer: B
Explanation
The correct answer is B, as the information radiator provides real-time visibility into the sprint's progress and is designed for stakeholders to access updates easily. Options A, C, and D are less efficient since they either require the executive's presence or do not utilize the tools specifically meant for sprint updates.