PMI Agile Certified Practitioner (PMI-ACP) — Question 182
Chart Base on the burn down chart, what is the iteration's status?
Answer options
- A. It trended ahead of scheduled and completed everything on time
- B. It took more time than expected and had to be lengthened
- C. It trended behind schedule and did not complete everything on time
- D. It took less time than expected and had to be shortened
Correct answer: C
Explanation
The correct answer is C because it accurately describes a situation where the project is not on track and has not met its deadlines. Options A, B, and D all suggest that the iteration is performing better than expected or has been adjusted positively, which contradicts the indication of being behind schedule.