PMI Agile Certified Practitioner (PMI-ACP) — Question 168
During iteration planning, it was determined that an epic should be decomposed.
What was the determining factor?
Answer options
- A. Size and priority
- B. Minimum marketable features
- C. Release plan
- D. Sprint mapping
Correct answer: A
Explanation
The correct answer is A, as the size and priority of an epic are crucial in deciding whether it needs to be decomposed for better manageability. Options B, C, and D focus on other aspects of project planning but do not directly address the need for breaking down an epic based on its size and urgency.