PMI Agile Certified Practitioner (PMI-ACP) — Question 166

A development team, new to scrum, questions the need to collect metrics on team performance. While team members understand velocity and burn down, they feel that once velocity becomes settled it is needless to keep track.
What should the agile coach tell the team?

Answer options

Correct answer: C

Explanation

The correct answer is C because tracking velocity provides a reference point that helps the team evaluate the impact of their continuous improvement efforts over time. Options A and D focus on external assessments and communication rather than internal improvement, while B suggests comparison with other teams, which may not directly benefit the team's own growth.