PMI Agile Certified Practitioner (PMI-ACP) — Question 154

A project's first iteration contains item A, and its second iteration contains item B. The first iteration is behind schedule, which will impact the second iteration.
Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?

Answer options

Correct answer: A

Explanation

The correct answer is A because it is important to focus on completing the first iteration before starting on the second, ensuring that all tasks are properly addressed. Options B and C could lead to further complications by overcommitting resources or bypassing necessary approvals. Option D, while it logs the issue, does not prioritize the need to complete the first iteration before moving forward.