PMI Agile Certified Practitioner (PMI-ACP) — Question 152
The executive leadership wants to understand ways to better deliver on time and on budget.
What can the project team do to assist in achieving the organizational goal?
Answer options
- A. Maintain and review a lessons learned repository to improve delivery of future projects
- B. Ask each team member to post corrective action to the backlog
- C. Engage the project management office (PMO) to take responsibility identifying lessons learned on projects
- D. Perform a root cause analysis to identify alternative approaches for performing the next project
Correct answer: A
Explanation
Maintaining and reviewing a lessons learned repository allows the project team to leverage past experiences to improve future project delivery, which aligns with the organizational goal. The other options, while potentially useful, do not directly create a systematic approach to utilizing past project insights like option A does.