PMI Agile Certified Practitioner (PMI-ACP) — Question 149
What should a team consider when calculating the effort needed to complete a product backlog?
Answer options
- A. The increase in velocity and cost
- B. A buffer in the sprint to mitigate unexpected risks
- C. Assigning extra points to each task to allow time for changes
- D. Stories describing infrastructure tasks and analysis tasks
Correct answer: B
Explanation
Option B is correct because having a buffer in the sprint helps the team manage unexpected challenges effectively. Options A and C do not directly address the estimation of effort needed, and option D focuses on types of tasks rather than the effort calculation.