PMI Agile Certified Practitioner (PMI-ACP) — Question 144
What should the agile practitioner know about tracking velocity?
Answer options
- A. A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25
- B. A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25
- C. A team that consistently meets its planned velocity is more efficient that a team that consistently exceeds its planned velocity
- D. A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity
Correct answer: C
Explanation
The correct answer is C because a team that consistently meets its planned velocity demonstrates a stable and reliable performance, which is crucial for effective sprint planning. In contrast, a team that frequently exceeds its planned velocity may not be sustainable in the long run, as it could lead to burnout or unrealistic expectations. Options A and B incorrectly equate velocity with efficiency, while D misrepresents the implications of exceeding planned velocity.