PMI Agile Certified Practitioner (PMI-ACP) — Question 141
After completing the release plan, the team realizes that the project is very likely to have a negative ROI.
What should the team do?
Answer options
- A. Prioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI
- B. Replace some team embers to reduce the release costs and minimize a negative ROI
- C. Perform a root-cause analysis to remove waste from the delivery process and increase the ROI
- D. Communicate the risk of a negative ROI to the stakeholders, and update the release plan
Correct answer: C
Explanation
The correct answer, C, involves analyzing the underlying issues that lead to inefficiencies in the delivery process, which can help improve the ROI. Options A and B address symptoms rather than the root cause, while D focuses on communication without taking actionable steps to resolve the issue.