PMI Agile Certified Practitioner (PMI-ACP) — Question 13
A new product owner shares the product vision during the team launch event. The team asks for clarification on the product roadmap and its high-level features.
What should the product owner do?
Answer options
- A. Determine the required tasks for implementing the high-level features
- B. Identify the detailed design for the high-level features
- C. Prioritize the product backlog for the upcoming release
- D. Estimate the user stories in the iteration backlog
Correct answer: C
Explanation
The correct answer is C because prioritizing the product backlog helps the team understand which features to focus on first based on the product vision. Options A and B are not the immediate concerns since the team needs clarity on priorities rather than task details or design. Option D is also incorrect as estimating user stories is a subsequent step that follows prioritization.