PMI Agile Certified Practitioner (PMI-ACP) — Question 120

An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action.
What should the team do?

Answer options

Correct answer: D

Explanation

The correct answer is D because reestimating the backlog items while including contingency helps set realistic expectations for stakeholders and addresses the velocity issues. Option A may not address the root of the velocity problem, and options B and C focus on increasing capacity or discussing issues without directly addressing the need for accurate estimation and expectation management.