PMI Agile Certified Practitioner (PMI-ACP) — Question 115

During project inception, an agile practitioner engages the stakeholder to ensure alignment on the project's strategy and vision. The stakeholder asks for detailed requirements, design, and delivery plans.
What should the agile practitioner do?

Answer options

Correct answer: B

Explanation

The correct answer is B because it is essential for the agile practitioner to establish clear expectations about the level of detail that is appropriate during the inception phase. Answer A is incorrect as providing excessive detail might not align with agile principles. Option C is not suitable because while agile practices may not focus on detailed documentation, some level of information can still be communicated. Option D is not ideal as it shifts responsibility rather than addressing the stakeholder's request directly.