PMI Agile Certified Practitioner (PMI-ACP) — Question 112
How can an agile team working on a new product ensure alignment with external stakeholders?
Answer options
- A. Ask the product owner to provide a detailed product specification document
- B. Conduct story-mapping exercises to clarify deliverables and release priorities
- C. Hold a kick-off meeting to assign roles and responsibilities
- D. Work with the scrum master and stakeholders to ensure agile principles are followed
Correct answer: B
Explanation
The correct answer is B, as story-mapping exercises help visualize the product requirements and prioritize deliverables, fostering alignment with stakeholders. Option A may lead to excessive documentation, which is contrary to agile practices. Option C focuses on internal roles, which doesn't directly address stakeholder alignment, while option D is about adhering to principles rather than ensuring stakeholder engagement.