PMI Agile Certified Practitioner (PMI-ACP) — Question 105
An agile practitioner wants to ensure that stakeholders have current information about a project's progress.
What should the agile practitioner do?
Answer options
- A. Regularly circulate an updated, detailed version of the project plan
- B. Frequently update the online project management office (PMO) repository site
- C. Invite the stakeholders to daily stand ups
- D. Post a project board in an area where all can view it
Correct answer: D
Explanation
The correct answer, D, is effective because it allows stakeholders to see real-time updates on the project's progress. Options A and B focus on documentation, which may not be as immediately accessible or engaging, while option C may not ensure all stakeholders can participate or stay informed.