PMI Agile Certified Practitioner (PMI-ACP) — Question 102

An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay, and is planning to start the marketing campaign and announce the release.
What should the agile coach do?

Answer options

Correct answer: D

Explanation

The correct answer is D, as it is crucial for the agile coach to communicate the delay to the marketing stakeholders to prevent misinformation and manage expectations. Answer A focuses on improving team velocity, which is not an immediate solution to the communication issue. Answer B suggests ignoring the problem, which could lead to greater issues, and Answer C, while valuable for future improvements, does not address the current situation effectively.