Program Management Professional (PgMP) — Question 94
What cost estimating approach uses the work breakdown structure to create a cost estimate?
Answer options
- A. Analogous
- B. Definitive
- C. Top down
- D. Parametric
Correct answer: B
Explanation
The correct answer is B, Definitive, as it relies on a detailed work breakdown structure to provide an accurate cost estimate. Analogous and parametric methods are based on historical data or statistical relationships, while top-down estimating does not utilize a detailed breakdown of work.