Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.

Answer options

Correct answer: C, D

Explanation

The correct answers are C (Total float) and D (Free float) because these terms are recognized in project management for describing the amount of time that a task can be delayed without affecting the project's overall timeline. Options A (Half float) and B (Full float) are not standard terms in this context, making them incorrect.