Program Management Professional (PgMP) — Question 80
A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?
Answer options
- A. Reactionary risks
- B. Chain risks
- C. Secondary risks
- D. In flux risks
Correct answer: C
Explanation
The correct answer is 'Secondary risks' because these are risks that emerge as a direct result of implementing a risk response. The other options do not accurately describe risks that originate from prior risk management actions, making them incorrect.