Program Management Professional (PgMP) — Question 71

The program charter for a new, five-component program has been approved.
What should the program manager use to communicate the program's intended direction and the linkage between organizational strategies and planned work?

Answer options

Correct answer: A

Explanation

The Program roadmap is the correct answer as it visually outlines the program's objectives and how they align with organizational strategies. The Program charter outlines the program's purpose but does not detail the strategic alignment. The Program business case focuses on the justification for the program and the Program management plan details execution but lacks the strategic overview.