Program Management Professional (PgMP) — Question 56

A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment.
Where should the program manager document this?

Answer options

Correct answer: D

Explanation

The correct answer is D, the Program quality management plan, as it outlines how quality will be managed throughout the program, including user acceptance testing. Options A and B do not specifically focus on quality management processes, while C pertains to specific tests rather than the broader quality assurance framework.