Program Management Professional (PgMP) — Question 49
A company is releasing a new product geared toward a specific geographic area. The program manager has received the program objectives and developed the program roadmap, which consists of six program components. Approval from the program governance board has been obtained.
What is the program manager's next step?
Answer options
- A. Assign project managers and resources
- B. Classify the program's benefits
- C. Identify the program sponsor and program stakeholders
- D. Develop the program business case
Correct answer: C
Explanation
Identifying the program sponsor and stakeholders is crucial as it establishes key relationships and ensures that all parties are engaged and informed about the program's direction. Assigning project managers and resources, classifying benefits, and developing the business case are important but come after identifying the right stakeholders to involve in the process.