Program Management Professional (PgMP) — Question 382

In a transformational program, all projects are on track and delivering their objectives. However, stakeholders are hesitant to take on the new processes, because performance in the current environment may not be representative of actual performance. Stakeholders fear the program will fail to provide the service required.

To assure positive performance in the current environment, what should the program manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because it focuses on communicating with stakeholders to build their confidence in the new processes by emphasizing their superiority over existing ones. Options A and C do not directly address stakeholder concerns, while option B suggests changing processes rather than reinforcing the benefits of the new ones.