Program Management Professional (PgMP) — Question 377
A leading high-technology enterprise is initiating a new adaptive program. During the delivery phase, one component falls behind the expected schedule because another component is sharing resources.
Which documents should the program manager update?
Answer options
- A. Program roadmap and program schedule management plan
- B. Program roadmap and program master schedule
- C. Program roadmap and schedule model principles
- D. Program roadmap and program risk register
Correct answer: B
Explanation
The correct answer is B because the program master schedule is essential for tracking the overall timeline and dependencies between components. Updating the master schedule and the roadmap ensures that all stakeholders are aware of the current status and any necessary adjustments. Options A, C, and D do not directly address the scheduling impact caused by the resource conflict.