Program Management Professional (PgMP) — Question 35

You are the project manager of a construction project. You have to close a phase of the project. Which is the only technique (or tool) available in the Close Project or Phase process?

Answer options

Correct answer: C

Explanation

The correct answer is C, Expert judgment, as it is specifically identified as the technique used in closing a project phase. The other options, while useful in project management, do not serve as formal techniques in the Close Project or Phase process.