Program Management Professional (PgMP) — Question 35
You are the project manager of a construction project. You have to close a phase of the project. Which is the only technique (or tool) available in the Close Project or Phase process?
Answer options
- A. Change control meetings
- B. Project management information system
- C. Expert judgment
- D. Observations
Correct answer: C
Explanation
The correct answer is C, Expert judgment, as it is specifically identified as the technique used in closing a project phase. The other options, while useful in project management, do not serve as formal techniques in the Close Project or Phase process.