Program Management Professional (PgMP) — Question 33

A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated, only 60 percent has been achieved.
What should the program manager do to ensure benefits realization?

Answer options

Correct answer: D

Explanation

The correct answer is D because updating the program schedule and escalating the issue to the PMO can help expedite progress and mitigate delays. Options A, B, and C focus on analysis and communication but do not directly address the immediate need to accelerate work and ensure benefits realization.